The Pulaski County Special School District will be working closely with the project team from KINCO Constructors for the Mills University Studies High School facilities projects. During this process, PCSSD will share project updates on the Mills University Studies HS website and Facebook page.
Classroom Addition
Concrete: Bass will start working on the foundations at the Classroom Addition this week.
MEP: Plumbers and electricians are going to start working on the underground rough-ins this week.
Arena
Earthwork: James A Rogers will be done demoing the existing storm drains at the Arena this week. The building pad will be completed this week as well.
Site Utilities: Diamond will continue to install the sanitary sewer around the Arena throughout the week.
Softball
Storm Drainage: James A Rogers will start installing RCP at the softball field this week.